Your publication puts its finger on a real subject, Mehdi. Teams are sometimes asked to meet deadlines while continually changing the conditions under which they must meet them.
An order becomes a priority. Another passes behind. Supplies were revived, manufacturing interrupted, and series changeovers brought forward. Then we are surprised to see assets under management increase and productivity deteriorate.
From my perspective as site director and COO, the first question would be: what has changed to justify this new priority, and have we measured its consequences?
An accepted emergency often involves several customers.
Advancing an order on a saturated resource is equivalent to shifting another. The cost is reflected in the additional adjustments, the exceptional transport, the hours mobilized and the commitments that will have to be renegotiated.
The urgency can be legitimate. It then deserves an explicit arbitration: what we gain, what we move and who assumes the decision.
It is also necessary to distinguish between PDP, which engages a production and resource trajectory, and daily adjustments to the scheduling. A breakdown requires a response. It should not lead to the constant rebuilding of all commitments.
Useful stability consists in protecting a horizon consistent with supply times, manufacturing cycles and the actual capacity of the workshops. Exceptions must remain visible and their effects understood.
The reliability of the plan commits the management.
Can trade promise a date without capacity validation? Do operations have a right to alert? Are purchases receiving needs that are stable enough to engage suppliers?
These questions go beyond the planning department. They affect the way in which the company makes and keeps its commitments.
This is also a point that I explore in the recruitment of industrial managers and supply chain managers at Antal International: have they been able to build these arbitration rules and enforce them, even under commercial pressure?
Before asking teams to be more responsive, let's look at the stability we give them to work.
In your organizations, who can change a production priority, and with what visibility on the consequences?